Projects
Polyroad - Yet Another Alternative
Introduction
In late 2000/early 2001, a project on the Winton-Hughenden road
suffered significant distress, very early in the life of the pavement (in
fact, one section had severe wheel rutting as a result of construction
traffic).
The problem was later identified, through audit, that, although the
base material generally met the specification, it was a very sandy
material which completely lacked cohesion. As a result, when trafficked,
especially after rainfall, the pavement severely rutted and shoved.
Several sections were repaired using a combination of lime/flyash/cement
through a pug/pave operation. This was successful, however the already
placed/sealed sections couldn't be economically treated the same way.
An alternative was sought which allowed treatment insitu, while
providing a waterproof, stable unbound pavement material.
Problem Identification
When the materials for the project were tested through audit, the
results showed gradings that were within spec and plastic properties that
had very low PI and virtually no shrinkage.
These materials are very strong when tested in a CBR mould in a
confined condition, but when tested in an unconstrained situation, such as
a pavement, especially on the outer wheel path zone, there is little shear
strength, hence shoving and
rutting is prevalent under load.
The "conventional" treatment for this sort of failure is to recycle the
base with an addition, usually cement (type GB). However, the pavement
sits on a subgrade that is a residual "black" highly expensive CH clay.
Experience has shown that a rigid layer over an expansive layer
displays aggressive fatigue cracking and shrink/swell heave and the
pavement disintegrates early in it's life (though not as fast as the
original construction).
An alternative solution was sought to modify the properties of the
sandy base gravel to provide cohesion, waterproofing and shear strength,
while maintaining a flexible layer.
Product Options
A range of products was considered, including lime, lime/cement, foamed
bitumen and fine grained plastic binder. In addition, a product that has
been rarely used in Queensland was considered, called Polyroad.
The properties of Polyroad are available through the
www.polyroad.com.au and it is not intended to review these properties.
However, the conditions under which it works and the material properties
were sought from the supplier to assess the possibility of using the
material.
The base gravel lacked fines (ie only around 5% passing the 75um sieve)
and had a PI around 4% with LS between 0 and 2.6%.
The base pavement was 200 mm thick, sitting on a subgrade (CH clay)
with PI around 27 - 41% and LS 12.2 and 18.4%. At the time, it was thought
that the mixing of the base material with a percentage of the black soil
would provide a suitable grading and plastic properties, suitable for the
addition of Polyroad. When the materials were added together in the lab,
the CBR dropped to 29 and 32 for the two samples prepared. In addition,
the swell results were very high, showing that the in service performance
would be poor.
The supplier of Polyroad advised that the target maximum PI for the
finished pavement after the addition of Polyroad is around 8%. As such lab
testing was undertaken to determine the dose rate of hydrated lime and
PR21L Polyroad (which includes 33% hydrated lime) to achieve a maximum PI
of 8%. The dose rate settled on after extensive mix design and Eades and
Grimm lime demand testing was 2% hydrated lime and 1.5% Polyroad.
The testing showed that a sample of PI 32.8 and LS of 19.2 reduced to
PI 10.4 and LS 2.8 with 2% hydrated lime and to PI 7.4 and LS 2.6 after 2%
lime and 1.5% Polyroad.
Additional testing was also undertaken to assess the CBR of the various
materials, with no treatment and with lime/Polyroad and also parallel
testing was undertaken to determine the strength of the material in the
presence of water. The results are as follows, for the CBR testing:
Additive
|
Test Conditions
|
CBR
|
| no additive |
unsoaked |
29 |
| no additive |
unsoaked |
32 |
| 2% lime + 1.5% Polyroad |
unsoaked |
180 |
| 2% lime + 1.5% Polyroad |
unsoaked |
160 |
| 2% lime + 1.5% Polyroad |
soaked |
220 |
| 2% lime + 1.5% Polyroad |
soaked |
180 |
The samples were also placed in a tank of water to determine the effect
of water under accelerated conditions. A photographic record was kept
hourly for the first few hours then daily then weekly, for about two
months. The results were quite dramatic, with the untreated gravel/clay
disintegrating within two hours and the lime treated gravel/clay
dissolving a significant amount after about two weeks but the Polyroad
lost only a few grains of material and none of the strength over the two
months and when removed from the tank, the water had only penetrated a few
millimetres into the sample.
Construction Process
The section that showed distress early in the pavement life was 1.3km
long. The testing undertaken was based on recycling 200mm of granular base
with 50mm of CH clay subgrade. The construction process adopted as a
result of the laboratory tests was as follows:
On day 1: place 2% by weight lime double mix to 250mm depth
incorporating sufficient moisture for compaction/hydration lightly
compact the mix.
On day 2: add 1.5% Polyroad and mix the materials together, adding
sufficient moisture for compaction compact trim seal/reseal
The project went well, except for some problems with moisture control
on the first day. The Polyroad has to be placed dryer than normal as the
Polyroad makes the clay particles hydrophobic and it is extremely hard to
put water into the material (exactly what it is designed to do). The
Polyroad also has a lubricating action, therefore lower moisture contents
can be used without compromising compaction density.
Conclusion
The trials using Polyroad have proven the product viable and it is
intended to continue trialling the material in selected locations to
determine the most cost effective and best long term situations for the
product life. The product has very great potential applications where we
require a flexible pavement configuration while maintaining both wet and
dry strength over a very long time period. It is intended to utilise the
remaining material stored at the shire depot on similar repair work south
of this project, once again on residual black CH clays.
However, it is hoped that we will not have to use a product such as
this to rectify project construction problems in future.
Report by:
David Atkinson
Regional Advisor (Asset Management)
Main Roads, Queensland
Email -
david.j.atkinson@mainroads.qld.gov.au
To download a copy of this
report in PDF (101KB) format Click here.
Warning: This file may be slow to open. To
save and view on your local computer right click on link and select 'Save
Target As...'.
For more information Contact Us
Back to Top
|