State Highway SH17, Newell Highway
- 27Km North of West Wyalong - Floodways
Site Details:
- AADT = 3500
- Percentage heavy vehicles = 45%
- 20 Year ESAs = 3 X 107
- Constructed December 1998
- 200mm thick in situ stabilisation with Polyroad PR21L @ 1.5% spread
rate
- Conventional cutback bitumen seals
- Competitively Tendered - Contract Construction
- Floodways included in stabilisation
Comments:
- Retained formation shape
- No wheel path rutting
- No shoulder deformation
For more information Contact Us