| |
|
|
Technical Information
Polyroad Performance in the Field
State Highway SH17, Newell Highway
- 35Km North of West Wyalong
Site Details:
- AADT = 3500
- Percentage heavy vehicles = 45%
- 20 Year ESAs = 3 X 107
- Constructed June 1996
- 200mm thick in situ stabilisation with Polyroad PR21L @ 1.5% spread
rate
- Conventional cutback bitumen seals
Comments:
- Retained formation shape
- No wheel path rutting
- No shoulder deformation
For more information Contact Us
Back to Top |
Back to Case Studies
|
|